The blowout leaderboard

Government projects ranked by how many times over the first public figure they now cost. Together they are $95.6bn over.

  1. 1BOM website$4.1m → $96.5m23.5×

    $4.1m was the figure first given to the public.

  2. 2Snowy 2.0$2bn → $22.2bn11.1×

    Target cost. Up to $25bn with contingency; transmission not included.

  3. 3Inland Rail$10.7bn → $45.6bn4.3×

    Both P90 estimates for the full Melbourne to Brisbane line. Only Beveridge to Parkes is now being built.

  4. 4Cross River Rail$5.4bn → $19bn3.5×

    Queensland Government figure (Oct 2025). It includes 25 years of tunnel maintenance and network works; Labor disputes counting them.

  5. 5North East Link$10bn → $26.1bn2.6×

    Victoria's December 2023 estimate. Includes the Eastern Freeway and M80 upgrades added since.

  6. 6Hunter-class frigates$35bn → $45.6bn1.3×

    2020 Force Structure Plan estimate for nine ships. The program is now six ships; close to $27bn is allocated for the first three, including the Osborne shipyard.

Think you could have guessed? Take the blowout quiz →

"First figure" is the first cost estimate given to the public. "Now" is the latest official estimate. Each project links to a story with the full timeline and sources.